REM testing toward the airport reaches a new milestone
Project progress
Published on
Since October 17, dynamic testing of the REM in preparation for the opening of the YUL-Aéroport-Montréal-Trudeau branch has entered a new phase: REM cars are now operating automatically at high speed as far as Marie-Curie station.
The objective of this new testing phase is to replicate operating conditions on the network, with REM cars reaching speeds of up to 100 km/h in certain areas!

Next steps
Testing will continue until the required quality, reliability and safety standards are met. We will then move on to the next steps:
- Expansion of the testing area, based on construction progress at YUL-Aéroport-Montréal-Trudeau station, under the responsibility of Aéroports de Montréal (ADM)
- Integration of the branch with the rest of the network
- Trial run
- Opening for passenger service
Under the schedule agreed upon with ADM, which is responsible for the construction of YUL-Aéroport-Montréal-Trudeau station, the target opening date remains late 2027.