Work in the Ville Mont-Royal sector

Construction activities
July 28–29 and August 5, 2018 7 a.m. to 7 p.m.
Montréal (Centre and Airport)

Où : Mont-Royal train station.

 

Nature of the work

On July 28 and 29, construction will include the placement of backfill on the west tracks. This important step will allow us to continue the preliminary work for setting up the construction site.

 

Impact and planned mitigation measures

  • The use of a power shovel may create noise; noise reduction measures will be taken if necessary.
  • Trucks will be used during the work period. The truck route will follow the Autoroute Métropolitaine, then Canora Road before entering the railway right-of-way using Jasper Avenue. The trucks will leave using the same route.