Work Schedule 2024
The timetable is provided for information purposes only and may evolve according to exchanges with our partners.
Click on the desired section:
Commissioning sequence
Construction and stations
Commissioning schedule
The schedule has been updated:
- Phase 1, South Shore to Central Station*: In service
- Phase 2, West Island, North Shore and Centre of Montréal segments: To be determined
- Phase 3, Airport segment: 2027, in collaboration with Aéroports de Montréal
*Griffintown-Bernard-Landry Station will be commissioned at a later date.
Downtown
- McGill: Interior design and finishing work on the station and mechanical equipment rooms. Gradual commissioning of equipment and systems (power supply, ventilation, etc.)
- Édouard-Montpetit: Continuation of the station’s interior design and start of exterior design and landscaping work.
- Mont-Royal Tunnel: Finalization of railway infrastructure installation.
Stations in the downtown sector
Centre of the Island of Montréal
- Finalization of the interior and exterior design of Canora, Ville-de-Mont-Royal, Côte-de-Liesse, Montpellier, Du Ruisseau and Bois-Franc stations.
- Finalization of installation of rail infrastructure (e.g., electrical system) in the sector.
- Finalization of installation of noise barriers.
Station in the centre of Montréal sector
West Island and airport
Towards Deux-Montagnes
- Continuation of construction work on Sunnybrooke and Pierrefonds-Roxboro stations and exterior design.
- Continuation of work to convert level crossings into railway overpass.
- Continued installation of rail infrastructure (e.g., electrical system, overhead contact lines) in the sector.
Towards Anse-à-l’Orme
- Finalization of interior and exterior work on Des Sources, Fairview-Pointe-Claire, Kirkland and Anse-à-l’Orme stations, including bus terminals.
- Installation of catenaries (cable pulling) to connect stations.
- Restoration around REM facilities and continuation of landscaping.
Towards YUL-Aéroport-Montréal-Trudeau
- Continuation of catenary installation (cable pulling).
- Finalization of restoration work near the facilities.
- Finalization of interior and exterior work on Marie-Curie station.
- Installation of tracks in the tunnel leading to the airport.
Stations in the West Island and Airport sector
North Shore
- Îles Laval and Sainte-Dorothée: Continuation of work on Île-Bigras station and exterior design (including civil work).
- Deux-Montagnes: Continuation of work on Deux-Montagnes and Grand-Moulin stations and finalization of exterior design.
- Along the railway right-of-way: Continued installation of railway infrastructure (e.g., electrical system); finalization of embankments and anti-graffiti work.
Stations in the North Shore sector
Keep informed about the work
Works info
Every week, we update the map of ongoing construction sites.
Newsletter
Stay up-to-date on the project’s major milestones.
Get in touch
Do you have any questions about the work? Contact a team member dedicated to your area.