Canora footbridge construction works

Canora footbridge construction works

Construction activities  | Major
December 2024 to summer 2025
Centre of Montréal

Nature of work : 

In order to finalize the construction of the Canora station accesses, a pedestrian bridge, connecting Jean-Talon Street West and the station entrance, will be installed in the coming months, as planned in the initial design. This footbridge will improve access to the station for users in the area.

Several phases will follow one another until the summer of 2025 to carry out this development: 

Schedule Works
Winter 2025 Preparation of the work area and foundations (excavation, slope reinforcement, drainage and concreting).  
Spring-Summer 2025 Construction of the footbridge and landscaping (formwork, concreting, backfilling, installation of fences, street furniture and plants).

Other communications will follow in the coming weeks to inform you of the detailed work, as well as the development improvement plan planned to ensure the integration of the station into the surrounding environment.

Impacts and mitigations measures :

  • Noise, vibrations, dust and trucking could be caused by this work.
  • Environmental monitoring will be deployed by environmental experts.
  • Appropriate mitigation measures will be put in place when necessary.

We invite you to contact us at [email protected] if you have any questions or comments.