Canora footbridge construction works
Nature of work :
In order to finalize the construction of the Canora station accesses, a pedestrian bridge, connecting Jean-Talon Street West and the station entrance, will be installed in the coming months, as planned in the initial design. This footbridge will improve access to the station for users in the area.
Several phases will follow one another until the summer of 2025 to carry out this development:
Schedule | Works |
Week of January 20, 2025, for approximately 2 weeks |
Hydro-Québec's preparatory work :
|
Winter 2025 |
Preparation of the work area and foundations :
Construction of the footbridge :
|
Spring / Summer 2025 |
Finishing and fitting out work :
|
Other communications will follow in the coming weeks to inform you of the detailed work, as well as the development improvement plan planned to ensure the integration of the station into the surrounding environment.
Impacts and mitigations measures :
- Existing safeguards will remain in place for the duration of the work.
- Noise, vibrations, dust and trucking could be caused by this work.
- Environmental monitoring will be deployed by environmental experts.
- Appropriate mitigation measures will be add when necessary.
We invite you to contact us at [email protected] if you have any questions or comments.