Complete closure of Des Sources Boulevard between Hymus Boul. and Highway 40

Complete closure of Des Sources Boulevard between Hymus Boul. and Highway 40

Road  | During the night only
Phase 1 : From October 31 to November 1, 9 PM to 5 AM. | Phase 2: From November 3 to November 4, 8 PM to 5 AM
West Island and Airport

Nature of the work :
A complete closure of Des Sources Boulevard will take place to allow for paving and marking work. The access road to Des Sources Boulevard will also be closed to traffic. Adequate signage will be in place to indicate detours to motorists.

This work will be carried out in the evening and night of:
•    Thursday, October 31, from 9 PM to Friday, November 1, 5 AM
•    Sunday, November 3, from 8 PM to Monday, November 4, 5 AM.
 

Impacts and mitigation measures : 
The objective of the REM project office and the NouvLR consortium is to mitigate the impacts on residents and ensure everyone’s safety by implementing appropriate measures.
-    A detour route will be set up to maintain traffic flow in the area. Adequate signage will be installed to inform motorists and pedestrians.


 

Des Sources Boulevard closure The map shows the location of the work

For all questions | 1 833 REM-INFO