Des Sources Station construction

Nature of the work:
REM construction work will continue throughout 2022:
- Elevated structure construction using launching gantry Marie, and installation of the new railway infrastructure (rails, electrical system, etc.)
- Des Sources Station construction

In preparation for the construction of the Des Sources station, Des Sources Boulevard must be reconfigured to facilitate vehicle traffic around the station. The first step is to reconfigure a section of the Highway 40 East ramp to southbound Des Sources Boulevard.
Planned Schedule |
Work |
Starting September 27, 2021 |
|
Starting October 1, 2021 |
|
Des Sources Station construction
Des Sources Station construction continues.
Calendar |
Work |
Winter 2022 / Spring 2022 |
|
Interstation between Des Sources and Fairview-Pointe-Claire stations
Construction of the overhead structure between Des Sources and Fairview-Pointe-Claire stations continues.
Calendar |
Work |
Winter 2022 / Spring 2022 |
|
Impacts and mitigation measures:
- Just as on any construction site, the work may cause noise, dust, vibrations and require trucking.
- Mitigation measures will be implemented as needed to mitigate impacts at the source (temporary noise barriers, low-noise equipment, white noise vehicles).
- Monitoring by environmental experts will take place throughout the work.
*Dates subject to change. Activities may be required before or after the scheduled times.
For all questions | 1 833 REM-INFO
Write us via the contact form of the "Contact us" page. You may contact us by phone on weekdays between 8:00 am and 5:00 pm.