Construction of Ville-de-Mont-Royal station

Construction of Ville-de-Mont-Royal station

Construction activities
Spring / Summer 2025
Centre of Montréal

Nature of work

Work continues at the site of the Ville-de-Mont-Royal station.  Here is an overview of the upcoming work for the next few months:

Schedule*
  Works
Spring / summer 2025
  • Electromechanical works and commissioning of building systems
  • Interior, exterior and landscaping works
  • Demobilization of certain construction site installations and restoration

 

Information provided for reference only. Some activities may be required before or after the scheduled time.*

Discover the Ville-de-Mont-Royal Station 

Ville-de-Mont-Royal Station 

Impacts and mitigation measures:  

The goal of the REM project office and the NouvLR consortium is to mitigate impacts on residents and ensure everyone's safety by implementing appropriate measures. 

  • Noise, vibrations, and dust may be generated by these works.
  • Some works will cause trucking in the neighborhood, and traffic obstructions may be put in place to minimize transit and secure construction zones.

For all questions | 1 833 REM-INFO

Write us via the contact form of the "Contact us" page. You may contact us by phone on weekdays between 8:00 am and 5:00 pm.