Continuation of work on the Alexander overpass
Road
Friday, March 18, 2022, during the day, 7 a.m. to 7 p.m.
Monday, March 21, 2022, during the day, 7 a.m. to 7 p.m.
Tuesday, March 22, 2022, during the day, 7 a.m. to 7 p.m.
Wednesday, March 23, 2022, during the day, 7 a.m. to 7 p.m.
Monday, April 4th, 2022, during the day, 7 a.m. to 7 p.m.
Friday, April 8, 2022, during the day, 7 a.m. to 7 p.m.
Monday 2 to Friday 6 May 2022, during the day, 7 a.m. to 7 p.m.
West Island and Airport
Nature of the work:
In order to continue the construction of the Alexander overpass, a partial obstruction of the street will be required to provide a safe working space to perform the post-tensioning of the overpass beams. During this period, traffic will be alternating.
This obstruction will occur daily between 7:00 a.m. and 7:00 p.m. on the following dates:
- Friday, March 18, Monday, March 21, Tuesday, March 22 and Wednesday, March 23 - obstruction completed
- Monday, April 4 and Friday, April 8 - obstruction completed
- Monday 2 to Friday 6 May 2022- obstruction completed
The following map shows the area concerned:
Impacts and mitigation measures:
The goal of the REM project office and the NouvLR consortium is to mitigate the impact on local residents and ensure everyone’s safety by taking all appropriate measures.
- Partial closure of Alexander Street, between Bonny and De la Station streets. Alternating traffic will be put in place to maintain traffic around the work site with the help of flaggers and appropriate signage.
- A sidewalk barrier on the west side will also be in place during the day. The sidewalk will remain accessible to pedestrians.
For all questions | 1 833 REM-INFO
Write us via the contact form of the "Contact us" page. You may contact us by phone on weekdays between 8:00 am and 5:00 pm.