Installation of overhead contact lines

Nature of work:
Work to install overhead contact lines will begin on September 6 along the REM route in the Deux-Montagnes sector. The work involves installing the pendulums and connections that will power the REM cars.
Impacts and mitigation measures :
Noise may be generated by the work. To minimize impacts, the following measures will be implemented:
‒ Activities are sequenced to move progressively through the segment and minimize the exposure period at any one point.
‒ Noise levels will be monitored by our environmental experts, and adjustments will be made according to the results.
‒ Working methods will be adapted to concentrate the activities likely to generate the most noise during the day.
‒ The use of the horn required by safety standards when reversing rail vehicles is prohibited between 7pm and 7am, and warnings of vehicle movements are governed by light signals.
‒ As far as possible, all vehicles on site, on track and on the ground, must be equipped with a white noise reversing alarm.
‒ Worksite communications are governed by personal radio transmitters or hand signals.
Illustration of catenary power supply:

For all questions | 1 833 REM-INFO
Write us via the contact form of the "Contact us" page. You may contact us by phone on weekdays between 8:00 am and 5:00 pm.