Landscaping work at Pierrefonds-Roxboro station

Landscaping work at Pierrefonds-Roxboro station

Construction activities
From the beginning of May until July 2025.
West Island and Airport

Nature of work :

As part of the work required to complete the Pierrefonds-Roxboro station and approach a new milestone, work on the exterior landscaping will have to take place from the beginning of May until July 2025.

Here is a high-level schedule of the expected work:

Calendar

Work

Early May 2025 to June 2025

Paving work and finalization of the sidewalks at the station and bus terminals:

  • Paving of parking lots
  • Concreting activities
  • Backfilling work
  • Correction of deficiencies
June 2025 to July 2025

Landscaping and finishing work around the station: 

  • Sowing
  • Furniture installation
  • Marking
  • Signge installation

 

Impacts et mitigation measures : 

  • Noise, vibrations, dust and trucking could be caused by this work.
  • Environmental monitoring will be deployed by environmental experts.
  • Other appropriate mitigation measures will be put in place when necessary.

For all questions | 1 833 REM-INFO

Write us via the contact form of the "Contact us" page. You may contact us by phone on weekdays between 8:00 am and 5:00 pm.