Nature of work :
As part of the work required to complete the Pierrefonds-Roxboro station and approach a new milestone, work on the exterior landscaping will have to take place from the beginning of May until July 2025.
Here is a high-level schedule of the expected work:
Calendar |
Work |
Early May 2025 to June 2025 |
Paving work and finalization of the sidewalks at the station and bus terminals:
|
June 2025 to July 2025 |
Landscaping and finishing work around the station:
|
Impacts et mitigation measures :
- Noise, vibrations, dust and trucking could be caused by this work.
- Environmental monitoring will be deployed by environmental experts.
- Other appropriate mitigation measures will be put in place when necessary.