Launching gantry “Anne” - Pierrefonds-Roxboro

Launching gantry “Anne” - Pierrefonds-Roxboro

Construction activities  | Major
Starting March 28, 2022, for approximately 5 months Spring 2022 / Summer 2022
West Island and Airport

Nature of the work:

The first phase of the elevated structure construction was completed with the construction of pillars in the centre of the railroad right-of-way in 2021.
In 2022, work will continue with the installation of concrete segments, which will form the deck of the elevated structure and on which the new REM infrastructure (rails, electrical systems, etc.) will be installed.

This work will be performed between 11th Avenue and Des Sources Boulevard using launching gantry Anne, Starting March 28, 2022, for approximately 5 months.

 

Step

Calendar

Traffic impact

Step 1 - Preparation of the launching gantry (positioning, tests, etc.)

From March 28 to 31, 2022, during the day, between 6:30 a.m. and 5 p.m

*Due to weather conditions, the obstruction is extended for Friday (April 1), Monday (April 4)

Completed
Stage 2 - Start-up of the assembly line (installation of the first segments)  From March 30 to April 2, during the day, between 6:30 a.m. and 5 p.m.  Completed
Stage 3 - Continued installation of voussoirs to Sources Blvd. Starting April 4, day and night, and weekends Ongoing

Impacts and mitigation measures:

  • This work will generate noise. For health and safety reasons, an alarm will be audible when the launching gantry will be in operation.
  • Night and weekend work is planned. Special mitigation measures will be put in place due to the nature of the work. Monitoring will be carried out by our environmental specialists.
  • Truck traffic is to be expected for the delivery of concrete segments near the pillars.
  • 11th Avenue will be completely closed between 4th Avenue and Jean-Brillant Avenue from March 28 to 31, 2022 between 6:30 a.m. and 5 p.m. Flaggers and appropriate signage will be deployed to facilitate traffic flow.

 

*Dates subject to change. Activities may be required before or after the scheduled times.

Elevated structure construction

The following elevated structure construction stages were performed simultaneously on the Anse-à-l’Orme branch:

Design of an access road and work areas

Completed

Relocation of public utilities as needed

In progress, continuing in 2022

Drilling for construction of the underground foundation caissons

Completed

Building the columns

Completed

Building the pier caps

Completed

Assembling prefabricated segments using the launching gantry, to form the deck on which the REM will run

Starting March 30, 2022

Installing the new rail infrastructure (rails, electrical system, etc.)

Coming in 2022 or 2023

Infography of the elevated structure and its componants, such as the foundation, the colums, the pier caps and the prefabricated segments.

For all questions | 1 833 REM-INFO

Write us via the contact form of the "Contact us" page. You may contact us by phone on weekdays between 8:00 am and 5:00 pm.