Lifting and installation of the Montgomery footbridge

Nature of work :
As part of the repair work on the Montgomery footbridge, in agreement with the Town of Mount Royal, an operation to lift and install the footbridge is to be expected in the coming days.
To do this, a crane will be installed at the intersection of Dunkirk Road and Montgomery Avenue. This work will begin on Monday, August 18 and will end on Saturday, August 23 at the end of the day.
Here are the planned steps:
Date |
Work |
Monday, August 18 |
Crane Assembly at the intersection of Dunkirk Road and Montgomery Avenue
Montgomery will be completely closed between 5 a.m. and 5 p.m. |
Friday, August 22 |
Lifting and installation of the Montgomery Footbridge |
Saturday, August 23 |
Dismantling of the crane
Montgomery will be completely closed between 5 a.m. and 5 p.m. |
Impacts and mitigation measures :
- Noise could be noticeable. The teams have been made aware of the management of their equipment in order to minimize the potential impact.
- Complete closure of Montgomery Avenue, between Churchill Road and Dunkirk between 5 a.m. and 5 p.m., on Monday, August 18 and Saturday, August 23.
- Adequate signage will be installed and flaggers will be on site to redirect vehicular and pedestrian traffic.
- Environmental monitoring will be deployed by environmental experts.