Obstruction on the Industriel Boulevard

Obstruction on the Industriel Boulevard

Road  | Major
Ongoing until August 2022
North Shore

Nature of the work:

In order to continue the construction of the Industrial Boulevard railway bridge, obstructions are to be expected in the area until August 2022. These obstructions will occur in sequence, according to the phases indicated below:

 

Phase

Date

Impact on traffic

1

Utility relocation and paving

Until June 14, 2022

Closing of the boulevard at the intersection of the REM route

2

Work on the railway bridge

From June 14 to 22

Alternating traffic at the intersection of the REM route

3

Installation of the beams - confirmed

From June 23 to 30

Closing of the boulevard at the intersection of the REM route

4

Work on the railway bridge - confirmed

Starting July 4,
for 4 weeks

Alternating traffic at the intersection of the REM route

 

The map below shows the obstruction and detour for Phases 1 and 3:

Closing of Industriel Boulevard, detour via Deux-Montagnes Boulevard

Impacts and Mitigation Measures:

  • Complete closure of traffic lanes on a portion of Industrial Boulevard. A detour route will be set up for automobile drivers, pedestrians and cyclists via Deux-Montagnes Boulevard. Flagmen and appropriate signage will be in place to facilitate traffic around the work site.
  • Police commercialization will be in place during Phases 1 and 3 to ensure traffic flow in the area during peak hours.
  • During all phases, pedestrians and cyclists will be able to cross the barrier at all times.
  • Shops and businesses will remain accessible at all times.

For all questions | 1 833 REM-INFO

Write us via the contact form of the "Contact us" page. You may contact us by phone on weekdays between 8:00 am and 5:00 pm.