Ongoing development work in the Marc-Cantin sector - obstructions
Road
| Major
From October 16th 2023, for about 6 weeks
South Shore
Nature of work:
Work to rehabilitate the Marc-Cantin sector following the arrival of the REM will continue into autumn 2023. Ultimately, this work will improve traffic flow in and around the Pointe-Saint-Charles business park.
Here are the details of the activities that will take place:
Phases | Étapes | Horaire |
---|---|---|
A | Development of the intersection of boul. Gaétan-Laberge and rue Marc-Cantin - Westbound |
From October 16, 2023. For about 3 weeks |
B | Development of the intersection of boul. Gaétan-Laberge and rue Marc-Cantin - Eastbound |
From October 30, 2023. |
Impacts et mitigation measures:
- The work will be carried out in several phases, during the day and at night.
- Phase A - Complete closure of a portion of boul. Gaétan-Laberge westbound from October 16, for approximately 3 weeks. A contra-flow lane will be set up to allow westbound access (Verdun).
- Phase B - Complete closure of a portion of Gaétan-Laberge Blvd. Gaétan-Laberge eastbound from November 6, for approximately 3 weeks. A contra-flow lane will be set up to allow eastbound access (downtown).
- Access to the Via Rail parking lot will be guaranteed at all times via boul. Gaétan-Laberge.
- Signallers and appropriate signage will be on hand to facilitate traffic flow.
- Some work will generate noise, dust, vibrations and truck traffic. Mitigation measures will be deployed whenever possible.
Phase A : Starting October 16, 2023
Phase B : Starting November 6, 2023