
Reconstruction of the overpass on chemin du Bord-de-l'Eau

Update - Work to complete the overhead structure:
Work to complete the overhead structure is underway and traffic will be alternating on a portion of Bord-de-l'Eau Road under the railway overpass on November 30, from 7 a.m. to 4 p.m. Flagmen will be on site during the day and the road will be reopened from 4 p.m. to 7 a.m.
Nature of work
The old railway overpass has been demolished and the reconstruction of the new overpass has begun in order to double the REM tracks and ensure the integrity of the structure.
Period | Nature of work |
---|---|
Winter 2022 |
|
Spring 2022 |
|
*This information is provided as an indication only. Some activities may be required before or after the scheduled time. Finally, all dates maybe subject to change without notice depending on weather conditions and operational needs of the site.
Anticipated impacts and mitigation measures
-
Noise, vibration, dust and trucking (for more information on the standards governing the construction phase, click here);
-
Partial obstruction on chemin du Bord-de-l'Eau with alternating traffic.

For all questions | 1 833 REM-INFO
Write us via the contact form of the "Contact us" page. You may contact us by phone on weekdays between 8:00 am and 5:00 pm.