Skip to main content
Slope stabilization work on embankments

Slope stabilization work on embankments

Construction activities  | Major
From April 11 to June 2022
Centre of Montréal

Nature of the work:

To strengthen the embankments on both sides of the rails, stabilization piles will be installed over the coming weeks. The machinery will generate significant noise while inserting the metal piles into the ground.  

The work will take place in the railroad right-of-way, between the Laird bridge and Montgomery footbridge. To perform this work, approximately 350 piles will be installed using vibratory pile driving, i.e. inserted into the ground using vibration. Seismographs will be installed nearby to ensure compliance with allowable vibration standards.

The work will mainly take place during the day, on weekdays from 7 a.m. to 7 p.m.

Work location

For all questions | 1 833 REM-INFO

Write us via the contact form of the "Contact us" page. You may contact us by phone on weekdays between 8:00 am and 5:00 pm.