Track and structural work - Canora station and Mont-royal tunnel

Track and structural work - Canora station and Mont-royal tunnel

Construction activities
The week of April 8 to the end of May 2024
Centre of Montréal

Nature of work

In order to continue the work surrounding Canora Station and the Mont-Royal tunnel, work is to be expected on the railway right-of-way between Canora Station and the Mont-Royal tunnel as well as in the tunnel itself. This work will begin the week of April 8, 2024 and will continue until the end of May 2024. 

Schedule Nature of work
Week of April 8 to the end of April 2024 Work on the tracks (concreting, formwork, etc.)
End of April to end of May 2024 Structural work in the tunnel

*It is possible that some work will have to be done over the weekend, but environmental experts will be following up to ensure that the criteria to which the project is subject are met.

 

Impacts and mitigation measures

  • Some work might generate noise, dust, trucking and vibrations.
  • To ensure compliance with the criteria to which the project is subject, monitoring will be carried out by environmental experts.