Partial closure of Côte-Vertu Boulevard

Nature of work
Work to relocate public utilities will be done on Côte-Vertu Boulevard to prepare for the construction of the future Montpellier station. Signage showing detours will be set up.
This work will be done in two phases and will not affect rail service. All station accesses will remain available. One of the two staircases of the Montpellier station will remain open at all times.
Anticipated work sequence and primary impacts
The schedule below may vary according to weather conditions and work progress.***


Impacts and mitigation measures
The goal of the REM project office and the NouvLR consortium is to mitigate the impact on surrounding residents and ensure everyone’s safety by taking all appropriate measures.
- This work will generate noise, vibration, dust and truck traffic. Mitigation measures will be implemented as needed to mitigate impacts at the source. In order to ensure the project’s noise, vibration and air quality criteria are met, monitoring by environmental experts will take place throughout the work.
For all questions | 1 833 REM-INFO
Write us via the contact form of the "Contact us" page. You may contact us by phone on weekdays between 8:00 am and 5:00 pm.