Relocation of utilities in the service road of Highway 40 West, Kirkland

Relocation of utilities in the service road of Highway 40 West, Kirkland

Road
May 10th to mid-July 2021, days and nights*
West Island and Airport

Nature of work:

From May 10th, relocation of sanitary sewer, storm and water mains will be performed in the service road of Highway 40 westbound, between Fairview Avenue and Exit 50.

 

Impacts and mitigation measures:

A complete closure of the service road is planned for a period of approximately 2 months. Appropriate signage will be installed indicating the proposed detour routes to the West Side Highway service road.

Highway 40 West:

  • From Highway 40 West, take exit 50.

Brunswick Boulevard:

  • From Fairview Avenue, left turn onto Brunswick Boulevard, then left onto Charles E. Frosst Street to merge onto the Highway 40 West service road.
Map presenting the work area and the closed service road

*Dates are subject to change. Activities may be required before or after the scheduled time.

For all questions | 1 833 REM-INFO

Write us via the contact form of the "Contact us" page. You may contact us by phone on weekdays between 8:00 am and 5:00 pm.