Application of anti-graffiti sealant

Du 5 au 18 septembre 2023
North Shore
Nature of work :
Cleaning work on the railway structure will be carried out from September 5 to 18, between 7 a.m. and 7 p.m., depending on weather conditions. High-pressure sand blasting will be used to apply the anti-graffiti sealant.
Impacts and mitigation measures :
The goal of the REM project office and the NouvLR consortium is to mitigate impacts on local residents and ensure the safety of all, by implementing appropriate measures.
- Traffic will be diverted onto Toupin Boulevard. Pedestrians and cyclists will be able to use the sidewalk provided.
- The work will generate significant noise and dust. Monitoring will be carried out by our environmental experts.
- The map below shows the phasing of the work:

For all questions | 1 833 REM-INFO