Obstruction – Partial closure of Deux-Montagnes Boulevard
Nature of work :
A significant obstruction will allow for the repair of the road structure, excavation, backfilling, and concreting of the sidewalks.
Depending on weather conditions, this work will be carried out in two phases, starting from November 4th, for approximately 6 months.
Phase 1 (November 4 to December 21, 2024)
A complete southbound closure of Boulevard Deux-Montagnes is planned (including the closure of the southbound sidewalk). Traffic will be redirected northbound with flaggers present during the day to facilitate the completion of these works.
Traffic will be possible at all times.
The map below shows the location of the works
Phase 2 (December 21, 2024 to April 2025)
In a second phase, once the snowfall begins and to facilitate vehicular traffic in this area, a single southbound lane closure on Boulevard Deux-Montagnes is planned. During this period, maintenance work to protect the curbs and paving stones is also planned.
Vehicular, pedestrian, and cyclist traffic will remain possible with the help of flaggers. A temporary pedestrian walkway will be set up for the duration of the works.
The map below shows the location of the works
Impacts and mitigation measures:
- Noise, vibrations, and dust may be generated by these works. Monitoring will be carried out by our environmental experts.
- Flaggers and adequate signage will be present on-site at all times during the works.