Infrastructure construction between the Mont-Royal tunnel and Canora station

Nature of the work:
To connect the REM infrastructures between the exit of the Mont-Royal tunnel and Canora station, a new work sequence will take place until spring 2023. Here is a breakdown of the scheduled activities:
Steps |
Schedule |
Pile drilling for the retaining walls under the Jean-Talon bridge |
Underway, until the end of November 2022 Work sequence lasting 3 weeks in November to continue installing the piles. During the day |
Construction of track slabs (excavation, backfill, concreting) |
Starting in early November 2022, for about 6 months During the day |
Construction of retaining walls under the Jean-Talon bridge |
From December 2022, for about 5 months During the day |
Reconstruction under the Canadian Pacific railway bridge (walls, slabs) |
From December 2022, for about 4 months During the day |
Other steps will follow and be communicated at a later date.
Impacts and mitigation measures:
- The work will take place mainly during the day on weekdays, and occasionally on weekends.
- This work may generate noise, dust and vibrations. Monitoring by environmental experts will take place during the work.
For all questions | 1 833 REM-INFO
Write us via the contact form of the "Contact us" page. You may contact us by phone on weekdays between 8:00 am and 5:00 pm.