Drainage work on André Avenue, Dorval

Drainage work on André Avenue, Dorval

Road
September 28 to October 2nd, 2020, day and night
West Island and Airport

Nature of the work

As part of the construction of the REM’s elevated structure in the West Island, André Avenue will be closed completely on September 28 to October 2nd to allow for drainage work. Local traffic will be allowed.

Here is the work schedule*:

Planned schedule

Work

September 28 to October 2nd,
day and night

  • Complete closure of André Avenue in both directions. The detour will be via Hymus Boulevard and the Highway 40 East service road.

 

The map below illustrates where traffic disruptions will occur

*The current sequence and set dates are subject to change without notice.

Impacts and mitigation measures:

Just as for any construction site, the work will generate noise, vibrations, dust, heavy truck traffic and traffic disruptions. Mitigation measures will be implemented to minimize the impacts. The REM project office and NouvLR consortium’s goal is to prevent or minimize impact on surrounding residents as much as possible and ensure safety by implementing all appropriate measures.

For all questions | 1 833 REM-INFO

Write us via the contact form of the "Contact us" page. You may contact us by phone on weekdays between 8:00 am and 5:00 pm.