Widening of De la Commune railway bridge
Construction activities
Spring - fall 2021
Mostly on weekdays, from 6:30 am to 7 p.m.
Downtown
Nature of the work
Begun in 2019, work to widen the Commune Bridge continues. They will be completed by the end of 2021. Here is a breakdown of upcoming activities:
Important: night work from August 19 to 21, 2021
Phase |
Schedule |
---|---|
Temporary relocation of the optical fiber |
|
Construction of the deck and north wall | Underway, until end of August approximately Mostly by day |
Waterproofing of the deck |
Summer 2021, for approximately 10 days (date to be announced) A work notice will be issued in connection with this work when the date is known. |
Installation of new railway infrastructures | Starting at the end of August 2021, for about 4 months By day |
Impacts and mitigation measures
- This work will generate noise and dust. Environmental specialists will conduct monitoring activities to ensure that the project complies with applicable noise and air quality criteria. Mitigation measures will be implemented where possible.
- Traffic obstructions will be maintained.
- Occasional night or weekend work is possible. This time slot is necessary for some work near the railroad tracks.
The work zone, as well as the bridge abutments to be built and the future widening, are presented below.
Bridge abutments to be built and the future widening
For all questions | 1 833 REM-INFO