Construction of the future Sunnybrooke Station

Construction of the future Sunnybrooke Station

Road
Winter / Spring 2023 Weekdays from 7am to 7pm and occasional weekends
West Island and Airport

Nature of the work:

Construction work continues at the location of the future Sunnybrooke Station .

Construction of the station

 

 Schedule

  Work

Winter / Spring 2023

  • Roofing and masonry

  • Electromechanical and electrical rooms (plumbing, ventilation, electricity, etc.)

  • Exterior envelope (curtain walls) and insulation

  • Sidewalk and paving of the street

*These dates are subject to change. Work will take place from 7 a.m. to 7 p.m. Work before and after this time period will allow for the mobilization and demobilization of equipment and site clean-up. 

Discover Sunnybrooke Station

Sunnybrooke Station

Architectural rendering of the Sunnybrooke Station

Impacts and mitigation measures:  

The goal of the REM project office and the NouvLR consortium is to mitigate the impact on local residents and ensure everyone’s safety by taking all appropriate measures. 

  • This work may generate noise, vibration and dust. 
  • Some of the work will require truck traffic in the neighbourhood; traffic pattern changes may be setup to minimize construction traffic and secure the construction zones.

For all questions | 1 833 REM-INFO

Write us via the contact form of the "Contact us" page. You may contact us by phone on weekdays between 8:00 am and 5:00 pm.