REM crossing over De Berne Street

Road
September 7-9, day and night
West Island and Airport

Nature of work

As part of the construction of the REM’s elevated structure on the West Island, De Berne Street will be closed completely from September 7-9 to finish construction of the elevated structure deck by installing the prefabricated segments.

The work schedule is as follows*:

Planned schedule

Work

September 7, 7 p.m. to September 8, 3 p.m.

  • Complete closure of De Berne Street, in both directions. Traffic will be detoured via Houde Street.
September 8, 7 p.m. to September 9, 3 p.m.
  • Complete closure of De Berne Street, in both directions. Traffic will be detoured via Houde Street.

 

The map below illustrates where traffic disruptions will occur from September 7-9:

*The current sequence and dates are subject to change without notice.

Impacts and mitigation measures

As with any construction site, the work will generate impacts such as noise, vibration, dust, heavy truck traffic and traffic disruptions. Mitigation measures will be implemented to minimize these impacts. The REM project office and the NouvLR consortium will endeavour to prevent or minimize the impact on surrounding residents as much as possible and ensure safety by implementing all appropriate measures.

For all questions | 1 833 REM-INFO

Write us via the contact form of the "Contact us" page. You may contact us by phone on weekdays between 8:00 am and 5:00 pm.