Work Schedule
The timetable is provided for information purposes only and may evolve according to exchanges with our partners.
Click on the desired section:
Commissioning sequence
Construction, stations and project milestones
Commissioning schedule
The schedule has been updated:
- Phase 1, South Shore to Central Station*: In service
- Phase 2, West Island, North Shore and Centre of Montréal segments: Fall 2025
- Phase 3, Airport segment: 2027, in collaboration with Aéroports de Montréal
Downtown
- McGill: Interior design and finishing work on the station and mechanical equipment rooms. Gradual commissioning of equipment and systems (power supply, ventilation, etc.) Demobilization of construction site facilities in the area, by the end of 2024.
- Édouard-Montpetit: Continuation of the station’s interior design and continuation of exterior design and landscaping work. Gradual commissioning of equipment and systems (power supply, ventilation, etc.).
- Mont-Royal Tunnel: Finalization of systems installation (beacons, axle counters, cameras, etc.). Beginning of static testing in the tunnel (validation of systems in place)
Stations in the downtown sector
Centre of Montréal
Dynamic testing begins in the centre of Montréal
Dynamic testing began in Pierrefonds-Roxboro and Sunnybrooke stations on August 7, 2024. For more information on the impacts of dynamic testing, please consult the construction info page.
- Finalization of the interior and exterior design of the Canora, Ville-de-Mont-Royal, Côte-de-Liesse, Montpellier, Du Ruisseau and Bois-Franc stations.
- Demobilization of certain construction site facilities and continued restoration of the site.
- Commissioning and validation of station systems (power supply, ventilation, etc.).
Station in the centre of Montréal sector
West Island and airport
Dynamic testing begins in the West Island
Dynamic testing began between Anse-à-l'Orme and Des Sources stations on September 3, 2024. Learn more. Testing began in in the Pierrefonds-Roxboro and Sunnybrooke station sectors on August 7, 2024. Learn more.
Deux-Montagnes branch
- Finalization of the interior and exterior design of the Sunnybrooke and Pierrefonds-Roxboro stations.
- Commissioning and validation of station systems (power supply, ventilation, etc.).
- Continuation of civil work for the parking lot and bus terminal at the Pierrefonds-Roxboro station.
Anse-à-l’Orme branch
- Finalization of interior and exterior work on Des Sources, Fairview-Pointe-Claire, Kirkland and Anse-à-l’Orme stations, including bus terminals.
- Restoration around REM facilities and continuation of landscaping.
YUL-Aéroport-Montréal-Trudeau branch
- Continuation of catenary installation (cable pulling).
- Finalization of restoration work near the facilities.
- Finalization of interior and exterior work on Marie-Curie station.
- Installation of electrical wiring in the tunnel leading to the airport.
Stations in the West Island and Airport sector
North Shore
Dynamic testing continues on the North Shore
Dynamic testing continues between the Saint-Eustache maintenance center and the Sainte-Dorothée station in Laval. Learn more about this milestone and upcoming phases of dynamic testing or learn more about impacts of dynamic testing in your sector.
- Îles Laval and Sainte-Dorothée: Finalization of work on the Île-Bigras station and exterior design (including civil work). Commissioning and validation of station systems (power supply, ventilation, etc.).
- Deux-Montagnes: Finalization of interior design work at the Deux-Montagnes and Grand-Moulin stations and finalization of exterior and landscaping work. Continuation of civil work to build the bus terminal and parking lot at the Deux-Montagnes station.
Stations in the North Shore sector
Keep informed about the work
Works info
Every week, we update the map of ongoing construction sites.
Newsletter
Stay up-to-date on the project’s major milestones.
Get in touch
Do you have any questions about the work? Contact a team member dedicated to your area.